A website project plan template lists every phase of a website build, the tasks inside each phase, and for every task the owner, the time it takes, what it produces and who signs it off. Below is a complete one, in tables you can copy into Google Sheets, Google Docs or Notion. It comes with a RACI chart, two sample timelines (an 8-week brochure site and a 14-week larger build) and a section on where feedback rounds and sign-offs go.
I build Huddlekit, a website feedback tool, so I mostly see projects at the review stage. The plans that hold up there have two things in common: the client's tasks have dates, just like the agency's, and every phase ends with one named person saying yes.
This post is the plan itself. For how to run the project around it (scope creep, waterfall or agile, the launch checklist), see my guide to website development project management.
How to read the template
Each phase is a table with one row per task. Owner is a role, so put names in once you have them. Days are working days for a typical small business site, so scale them to your project. Sign-off says who approves the deliverable, and Gate marks a sign-off the next phase waits for.
The roles are the PM (project manager, often the freelancer or account lead on a small team), the client lead (the one person on the client side who approves), the client team (everyone else who gives feedback), the designer, the developer and content (whoever writes the copy).
It works as a web development project plan template too: for custom functionality, add development and testing tasks to phases 5 and 6.
The website project plan template
Phase 1: Discovery
| Task | Owner | Days | Deliverable | Sign-off |
|---|---|---|---|---|
| Kickoff call with everyone who approves | PM | 1 | Call notes and a stakeholder list | None |
| Send the design questionnaire | PM | 1, plus client time | Answers from the client | None |
| Audit the current site and its analytics | PM, developer | 2 | What to keep, fix and drop | None |
| Agree two or three measurable goals | PM, client lead | 1 | Goals, each with a measure | Client lead |
| Write the project brief | PM | 1 | One-page brief | Gate: client lead |
A website design questionnaire saves most of the kickoff call.
Phase 2: Scope and plan
| Task | Owner | Days | Deliverable | Sign-off |
|---|---|---|---|---|
| Write the requirements document | PM, developer | 2 to 3 | Pages, features, integrations and what's out of scope | Client lead |
| Estimate the work | PM, developer | 1 | Estimate per phase, with contingency | PM |
| Write the proposal | PM | 1 | Price, terms and the number of feedback rounds | Client lead |
| Put dates and names on this plan | PM | 1 | Dated plan | Gate: client lead |
For the first three tasks, use the website requirements document template, the project estimate calculator and the proposal generator.
Phase 3: Content and sitemap
| Task | Owner | Days | Deliverable | Sign-off |
|---|---|---|---|---|
| Draft the sitemap | PM, designer | 1 | Every page, in a hierarchy | Client lead |
| Plan the content | PM | 1 | An owner and a due date for every page | Gate: client lead |
| Write or collect the copy | Content | 5 to 15 | Final copy for each page | Client lead, page by page |
| Gather logos, photos and brand files | Client team | Ongoing | One shared folder | None |
| Map old URLs to new ones | Developer | 1 | Redirect list | PM |
Copy runs alongside design, but give it a hard due date: late content is one of the most common reasons a build stalls.
Phase 4: Design
| Task | Owner | Days | Deliverable | Sign-off |
|---|---|---|---|---|
| Wireframe the key page templates | Designer | 3 to 5 | Wireframes | Client lead |
| Design the homepage and one key template | Designer | 4 to 5 | Mockups at desktop and phone width | Client lead |
| Run design feedback rounds | Client team, designer | 3 per round | Every comment resolved or deferred | None |
| Design the remaining templates | Designer | 5 to 10 | Full design set | Gate: client lead |
| Hand designs over to development | Designer | 1 | Files, styles and assets | Developer |
Phase 5: Build
| Task | Owner | Days | Deliverable | Sign-off |
|---|---|---|---|---|
| Set up hosting, the CMS and a staging site | Developer | 1 to 2 | A staging URL the client can open | None |
| Build templates in sign-off order | Developer | 10 to 20 | Working pages on staging | None |
| Add forms, integrations and analytics | Developer | 2 to 5 | Working forms and tracking | None |
| Enter the content | Developer, content | 3 to 5 | Every page with real copy and images | None |
| Show progress on staging | PM | Weekly | A short update to the client | None |
| Confirm staging is ready for review | PM | 1 | Complete staging site | Gate: PM |
Clients new to staging sites can read what a staging site is first.
Phase 6: Review and QA
| Task | Owner | Days | Deliverable | Sign-off |
|---|---|---|---|---|
| Run an internal QA pass | Developer, designer | 2 to 3 | Bugs found and fixed | PM |
| Client review, round 1 | Client team | 3 | Comments on the staging site | None |
| Triage and fix round 1 | PM, developer | 3 to 5 | Every comment fixed, deferred or priced | PM |
| Client review, round 2 | Client team | 3 | Comments on the staging site | None |
| Fix round 2 and run acceptance testing | Developer, client lead | 2 to 3 | Test results and a list of open items | None |
| Get written sign-off | Client lead | 1 | Sign-off by email or in your project tool | Gate: client lead |
The website QA checklist covers the internal pass, and the user acceptance testing template covers the last two tasks.
Phase 7: Launch and handover
| Task | Owner | Days | Deliverable | Sign-off |
|---|---|---|---|---|
| Run the pre-launch checklist and agree a launch time | Developer, PM | 1 | Checklist done, launch booked | Gate: client lead |
| Launch: domain, redirects, search engines allowed | Developer | 1 | Live site | None |
| Check forms, analytics and search console after launch | Developer | 1 | Launch-day checks | PM |
| Hand over access, documentation and training | PM | 1 | Handover pack | Client lead |
| 30-day review against the goals | PM, client lead | 1 | Results and a list for the next phase | None |
The website launch checklist and the handoff checklist cover the first and fourth tasks.
The RACI chart
RACI marks, for each deliverable, who does the work (Responsible), who has the final say (Accountable), who gives input (Consulted) and who only needs to know (Informed). The rule that matters: exactly one A per row.
| Deliverable | PM | Client lead | Designer | Developer | Content |
|---|---|---|---|---|---|
| Brief and goals | R | A | C | C | I |
| Requirements and scope | R | A | C | C | I |
| Timeline and budget | R | A | I | C | I |
| Sitemap and content plan | R | A | C | C | C |
| Page copy | C | A | C | I | R |
| Design | C | A | R | C | C |
| Staging build | A | I | C | R | I |
| Internal QA | A | I | R | R | I |
| Client review and sign-off | R | A | C | C | I |
| Launch | R | A | I | R | I |
| Handover and training | R | A | I | C | I |
The client lead is accountable for the copy even when someone else writes it, because someone has to say it's final. And internal QA belongs to your team: the client's review should start from a site you already believe works.
Other client stakeholders are consulted on the brief, copy and design, and informed on the rest. They give feedback. The client lead decides.
Two sample website project timelines
These are website project timeline templates for two common sizes. The last column is the one to send the client: it's what they owe you, and when.
An 8-week brochure site
For a site of 5 to 10 pages with a custom design, one approver and copy written by the client.
| Week | Phase | You deliver | The client delivers |
|---|---|---|---|
| 1 | Discovery, scope and plan | Brief, requirements and a dated plan | Questionnaire answers, scope sign-off |
| 2 | Sitemap and wireframes | Sitemap, content plan, wireframes | Sitemap sign-off, first drafts of copy |
| 3 | Homepage design | Homepage at desktop and phone width | Feedback within 3 working days |
| 4 | Remaining designs | Full design set | Design sign-off, final copy and photos |
| 5 to 6 | Build | Staging site, growing as pages are built | Quick answers to questions |
| 7 | Review and QA | Internal QA, then two client rounds | Feedback by each deadline, then sign-off |
| 8 | Launch and handover | Live site, handover, training | Go-live approval, domain access |
Week 4 carries the most risk: if the final copy and photos aren't in by then, the build runs on placeholder text and review turns into copy editing.
A 14-week larger build
For a site with 20 or more templates, content moving from an old CMS, a few integrations and several stakeholders.
| Weeks | Phase | You deliver | The client delivers |
|---|---|---|---|
| 1 to 2 | Discovery | Stakeholder interviews, site audit, brief | Analytics access, time with stakeholders |
| 3 | Requirements and plan | Requirements, estimate, dated plan | Scope and budget sign-off |
| 3 to 5 | Sitemap and content plan | Sitemap, content structure, redirect list | An owner for each section, sitemap sign-off |
| 4 to 6 | Wireframes | Wireframes of the main user journeys | Wireframe sign-off |
| 6 to 9 | Design | Design system and key templates, then the rest | Feedback on each batch, design sign-off |
| 8 to 12 | Build in two-week sprints | New templates on staging each sprint, integrations | Feedback on each sprint, final copy |
| 11 to 12 | Content migration | Old and new content in the new CMS | A check of each section |
| 12 to 13 | QA and acceptance testing | QA, two client rounds, test results | Feedback by each deadline, written sign-off |
| 14 | Launch and handover | Launch, first-week monitoring, training | Go-live approval |
The phases overlap on purpose: build starts on signed-off templates while others are still in design.
Where feedback rounds and sign-offs go
Most plans have one line that says "client review" with a week next to it. That's where timelines slip, so split it into dated steps:
- Open the round. Send one link to the staging site, with the deadline in the same message.
- Collect feedback for a fixed time. Three working days covers most rounds.
- Triage. A bug gets fixed, a change inside the scope gets done, and a change outside it gets estimated and logged.
- Fix and reply. Every comment ends fixed, deferred or priced, and the person who left it can see which.
- Start the next round on the new version, not on top of the last round's comments.
Two rounds per milestone (design, then build) is a common default. Put that in the proposal, with the price of a third.
A gate is a written yes from the client lead, by email or in your project tool. Work that depends on it starts after it. If you start early, which is normal, the plan should say that changes to an approved phase are change requests.
This is the stage I build Huddlekit for. The client opens the staging site from a link and comments on the page itself, with nothing to install, and every comment saves a screenshot along with the page, browser and screen size. On Pro and Team, each round starts clean on the same link while earlier rounds stay readable, and when a round's deadline passes you can switch the link to view only, so late comments don't arrive while you're fixing. For more on running the rounds, see how to review a website.
How to adapt the template
- A small site or a one-person studio. Merge phases 1 and 2 into one week, and shrink the RACI to the approver for each deliverable. Keep every gate: small projects slip on late content too.
- A theme or template build. Swap the wireframes and the full design set for theme setup and one styled homepage to sign off.
- A larger or custom build. Run phase 5 in sprints with a demo at the end of each. Add tasks for integrations, performance and accessibility testing (the accessibility checklist helps), plus a content migration phase.
- A fixed launch date. Plan backward from launch, put the content and design deadlines in the contract, and agree up front what gets cut if they slip.
- An agile team. Keep the gates on scope, design and launch, and run everything between them in sprints.
- A redesign of a site with search traffic. Give the redirect list and an SEO check their own tasks and owners, and watch search console closely after launch.
What most website project plans leave out
- Dates for the client's tasks. Copy, photos, feedback and sign-offs are tasks with owners and due dates, just like yours.
- Buffer. Leave a week of slack in any plan longer than six weeks, and don't spend it early.
- Holidays. Check both teams' calendars first. A client lead who's away in review week moves the launch, not just the review.
- Content entry. Formatting dozens of pages in a CMS takes days, not an afternoon.
- Access. Domain, DNS, hosting and third-party accounts. Ask in week 1.
- Legal review. Privacy pages, cookie consent and regulated wording can take weeks to approve in some industries.
Frequently asked questions
What should a website project plan include?
Every phase from discovery to handover, its tasks, and for every task an owner, a duration, a deliverable and a sign-off. Add a RACI chart, dated tasks for what the client owes you, feedback rounds with deadlines, and a gate at the end of each phase.
How long does a website project take?
The samples above put a 5 to 10 page brochure site at 8 weeks, and a larger build with migration and integrations at 14. Content and client approvals set the pace more often than design or code, which is why the client's tasks need dates too.
What is a RACI chart in a website project?
A table that marks who is Responsible, Accountable, Consulted and Informed for each deliverable. On a website project, its main job is naming one approver per deliverable, so someone can settle it when stakeholders disagree.
What's the difference between a project plan and a requirements document?
The requirements document says what the site must do: pages, features, integrations and how you'll test them. The project plan says who does the work, in what order and by when. Requirements come first. Here's a website requirements document template.
Can I use this template in Google Sheets, Excel or Notion?
Yes. Copy a table from this page and paste it into a spreadsheet, a doc or a Notion page, where it pastes as a table in most tools. Add start and end date columns to turn it into a schedule.
Put the gates in first
If you only take one thing from this template, take the gates. A plan where every phase ends with a named person saying yes, by a date, survives late copy, new stakeholders and the third round of "one small change".