Website project plan template: phases, tasks, sign-offs and sample timelines

•11 min read•Photo of Kevin LarssonKevin Larsson
Website project plan template: phases, tasks, sign-offs and sample timelines

A website project plan template lists every phase of a website build, the tasks inside each phase, and for every task the owner, the time it takes, what it produces and who signs it off. Below is a complete one, in tables you can copy into Google Sheets, Google Docs or Notion. It comes with a RACI chart, two sample timelines (an 8-week brochure site and a 14-week larger build) and a section on where feedback rounds and sign-offs go.

I build Huddlekit, a website feedback tool, so I mostly see projects at the review stage. The plans that hold up there have two things in common: the client's tasks have dates, just like the agency's, and every phase ends with one named person saying yes.

This post is the plan itself. For how to run the project around it (scope creep, waterfall or agile, the launch checklist), see my guide to website development project management.


How to read the template

Each phase is a table with one row per task. Owner is a role, so put names in once you have them. Days are working days for a typical small business site, so scale them to your project. Sign-off says who approves the deliverable, and Gate marks a sign-off the next phase waits for.

The roles are the PM (project manager, often the freelancer or account lead on a small team), the client lead (the one person on the client side who approves), the client team (everyone else who gives feedback), the designer, the developer and content (whoever writes the copy).

It works as a web development project plan template too: for custom functionality, add development and testing tasks to phases 5 and 6.


The website project plan template

Phase 1: Discovery

TaskOwnerDaysDeliverableSign-off
Kickoff call with everyone who approvesPM1Call notes and a stakeholder listNone
Send the design questionnairePM1, plus client timeAnswers from the clientNone
Audit the current site and its analyticsPM, developer2What to keep, fix and dropNone
Agree two or three measurable goalsPM, client lead1Goals, each with a measureClient lead
Write the project briefPM1One-page briefGate: client lead

A website design questionnaire saves most of the kickoff call.

Phase 2: Scope and plan

TaskOwnerDaysDeliverableSign-off
Write the requirements documentPM, developer2 to 3Pages, features, integrations and what's out of scopeClient lead
Estimate the workPM, developer1Estimate per phase, with contingencyPM
Write the proposalPM1Price, terms and the number of feedback roundsClient lead
Put dates and names on this planPM1Dated planGate: client lead

For the first three tasks, use the website requirements document template, the project estimate calculator and the proposal generator.

Phase 3: Content and sitemap

TaskOwnerDaysDeliverableSign-off
Draft the sitemapPM, designer1Every page, in a hierarchyClient lead
Plan the contentPM1An owner and a due date for every pageGate: client lead
Write or collect the copyContent5 to 15Final copy for each pageClient lead, page by page
Gather logos, photos and brand filesClient teamOngoingOne shared folderNone
Map old URLs to new onesDeveloper1Redirect listPM

Copy runs alongside design, but give it a hard due date: late content is one of the most common reasons a build stalls.

Phase 4: Design

TaskOwnerDaysDeliverableSign-off
Wireframe the key page templatesDesigner3 to 5WireframesClient lead
Design the homepage and one key templateDesigner4 to 5Mockups at desktop and phone widthClient lead
Run design feedback roundsClient team, designer3 per roundEvery comment resolved or deferredNone
Design the remaining templatesDesigner5 to 10Full design setGate: client lead
Hand designs over to developmentDesigner1Files, styles and assetsDeveloper

Phase 5: Build

TaskOwnerDaysDeliverableSign-off
Set up hosting, the CMS and a staging siteDeveloper1 to 2A staging URL the client can openNone
Build templates in sign-off orderDeveloper10 to 20Working pages on stagingNone
Add forms, integrations and analyticsDeveloper2 to 5Working forms and trackingNone
Enter the contentDeveloper, content3 to 5Every page with real copy and imagesNone
Show progress on stagingPMWeeklyA short update to the clientNone
Confirm staging is ready for reviewPM1Complete staging siteGate: PM

Clients new to staging sites can read what a staging site is first.

Phase 6: Review and QA

TaskOwnerDaysDeliverableSign-off
Run an internal QA passDeveloper, designer2 to 3Bugs found and fixedPM
Client review, round 1Client team3Comments on the staging siteNone
Triage and fix round 1PM, developer3 to 5Every comment fixed, deferred or pricedPM
Client review, round 2Client team3Comments on the staging siteNone
Fix round 2 and run acceptance testingDeveloper, client lead2 to 3Test results and a list of open itemsNone
Get written sign-offClient lead1Sign-off by email or in your project toolGate: client lead

The website QA checklist covers the internal pass, and the user acceptance testing template covers the last two tasks.

Phase 7: Launch and handover

TaskOwnerDaysDeliverableSign-off
Run the pre-launch checklist and agree a launch timeDeveloper, PM1Checklist done, launch bookedGate: client lead
Launch: domain, redirects, search engines allowedDeveloper1Live siteNone
Check forms, analytics and search console after launchDeveloper1Launch-day checksPM
Hand over access, documentation and trainingPM1Handover packClient lead
30-day review against the goalsPM, client lead1Results and a list for the next phaseNone

The website launch checklist and the handoff checklist cover the first and fourth tasks.


The RACI chart

RACI marks, for each deliverable, who does the work (Responsible), who has the final say (Accountable), who gives input (Consulted) and who only needs to know (Informed). The rule that matters: exactly one A per row.

DeliverablePMClient leadDesignerDeveloperContent
Brief and goalsRACCI
Requirements and scopeRACCI
Timeline and budgetRAICI
Sitemap and content planRACCC
Page copyCACIR
DesignCARCC
Staging buildAICRI
Internal QAAIRRI
Client review and sign-offRACCI
LaunchRAIRI
Handover and trainingRAICI

The client lead is accountable for the copy even when someone else writes it, because someone has to say it's final. And internal QA belongs to your team: the client's review should start from a site you already believe works.

Other client stakeholders are consulted on the brief, copy and design, and informed on the rest. They give feedback. The client lead decides.


Two sample website project timelines

These are website project timeline templates for two common sizes. The last column is the one to send the client: it's what they owe you, and when.

An 8-week brochure site

For a site of 5 to 10 pages with a custom design, one approver and copy written by the client.

WeekPhaseYou deliverThe client delivers
1Discovery, scope and planBrief, requirements and a dated planQuestionnaire answers, scope sign-off
2Sitemap and wireframesSitemap, content plan, wireframesSitemap sign-off, first drafts of copy
3Homepage designHomepage at desktop and phone widthFeedback within 3 working days
4Remaining designsFull design setDesign sign-off, final copy and photos
5 to 6BuildStaging site, growing as pages are builtQuick answers to questions
7Review and QAInternal QA, then two client roundsFeedback by each deadline, then sign-off
8Launch and handoverLive site, handover, trainingGo-live approval, domain access

Week 4 carries the most risk: if the final copy and photos aren't in by then, the build runs on placeholder text and review turns into copy editing.

A 14-week larger build

For a site with 20 or more templates, content moving from an old CMS, a few integrations and several stakeholders.

WeeksPhaseYou deliverThe client delivers
1 to 2DiscoveryStakeholder interviews, site audit, briefAnalytics access, time with stakeholders
3Requirements and planRequirements, estimate, dated planScope and budget sign-off
3 to 5Sitemap and content planSitemap, content structure, redirect listAn owner for each section, sitemap sign-off
4 to 6WireframesWireframes of the main user journeysWireframe sign-off
6 to 9DesignDesign system and key templates, then the restFeedback on each batch, design sign-off
8 to 12Build in two-week sprintsNew templates on staging each sprint, integrationsFeedback on each sprint, final copy
11 to 12Content migrationOld and new content in the new CMSA check of each section
12 to 13QA and acceptance testingQA, two client rounds, test resultsFeedback by each deadline, written sign-off
14Launch and handoverLaunch, first-week monitoring, trainingGo-live approval

The phases overlap on purpose: build starts on signed-off templates while others are still in design.


Where feedback rounds and sign-offs go

Most plans have one line that says "client review" with a week next to it. That's where timelines slip, so split it into dated steps:

  1. Open the round. Send one link to the staging site, with the deadline in the same message.
  2. Collect feedback for a fixed time. Three working days covers most rounds.
  3. Triage. A bug gets fixed, a change inside the scope gets done, and a change outside it gets estimated and logged.
  4. Fix and reply. Every comment ends fixed, deferred or priced, and the person who left it can see which.
  5. Start the next round on the new version, not on top of the last round's comments.

Two rounds per milestone (design, then build) is a common default. Put that in the proposal, with the price of a third.

A gate is a written yes from the client lead, by email or in your project tool. Work that depends on it starts after it. If you start early, which is normal, the plan should say that changes to an approved phase are change requests.

This is the stage I build Huddlekit for. The client opens the staging site from a link and comments on the page itself, with nothing to install, and every comment saves a screenshot along with the page, browser and screen size. On Pro and Team, each round starts clean on the same link while earlier rounds stay readable, and when a round's deadline passes you can switch the link to view only, so late comments don't arrive while you're fixing. For more on running the rounds, see how to review a website.


How to adapt the template

  • A small site or a one-person studio. Merge phases 1 and 2 into one week, and shrink the RACI to the approver for each deliverable. Keep every gate: small projects slip on late content too.
  • A theme or template build. Swap the wireframes and the full design set for theme setup and one styled homepage to sign off.
  • A larger or custom build. Run phase 5 in sprints with a demo at the end of each. Add tasks for integrations, performance and accessibility testing (the accessibility checklist helps), plus a content migration phase.
  • A fixed launch date. Plan backward from launch, put the content and design deadlines in the contract, and agree up front what gets cut if they slip.
  • An agile team. Keep the gates on scope, design and launch, and run everything between them in sprints.
  • A redesign of a site with search traffic. Give the redirect list and an SEO check their own tasks and owners, and watch search console closely after launch.

What most website project plans leave out

  • Dates for the client's tasks. Copy, photos, feedback and sign-offs are tasks with owners and due dates, just like yours.
  • Buffer. Leave a week of slack in any plan longer than six weeks, and don't spend it early.
  • Holidays. Check both teams' calendars first. A client lead who's away in review week moves the launch, not just the review.
  • Content entry. Formatting dozens of pages in a CMS takes days, not an afternoon.
  • Access. Domain, DNS, hosting and third-party accounts. Ask in week 1.
  • Legal review. Privacy pages, cookie consent and regulated wording can take weeks to approve in some industries.

Frequently asked questions

What should a website project plan include?

Every phase from discovery to handover, its tasks, and for every task an owner, a duration, a deliverable and a sign-off. Add a RACI chart, dated tasks for what the client owes you, feedback rounds with deadlines, and a gate at the end of each phase.

How long does a website project take?

The samples above put a 5 to 10 page brochure site at 8 weeks, and a larger build with migration and integrations at 14. Content and client approvals set the pace more often than design or code, which is why the client's tasks need dates too.

What is a RACI chart in a website project?

A table that marks who is Responsible, Accountable, Consulted and Informed for each deliverable. On a website project, its main job is naming one approver per deliverable, so someone can settle it when stakeholders disagree.

What's the difference between a project plan and a requirements document?

The requirements document says what the site must do: pages, features, integrations and how you'll test them. The project plan says who does the work, in what order and by when. Requirements come first. Here's a website requirements document template.

Can I use this template in Google Sheets, Excel or Notion?

Yes. Copy a table from this page and paste it into a spreadsheet, a doc or a Notion page, where it pastes as a table in most tools. Add start and end date columns to turn it into a schedule.

Put the gates in first

If you only take one thing from this template, take the gates. A plan where every phase ends with a named person saying yes, by a date, survives late copy, new stakeholders and the third round of "one small change".